Project case: the main roads
resurfacing around Nanjing Youth Olympics Games Stadium
Construction time: June, 2014
Construction site: 1, the main
streets around Nanjing Olympic Sports Center Stadium
2, the main streets around
Nanjing Longjiang Sports Stadium
3, Nanjing Tianyin Avenue,
airport connecting roads etc.
Construction technology: Freetech’s
hot in place repaving&remixing recycling
Project profile: Resurfacing of
the roads around the Youth Olympics Games Stadiums was an important”image
project” , in order to achieve”Green Youth Olympics Games”, Nanjing Municipal
Government required “low-carbon”, “environment-friendly” and “green” throughout
the whole construction process. Meanwhile, it’s required that all the
construction must be completed before June, 30th to ensure a clear
and blue sky for the games. Since the end of May, 2014, Freetech had started
the construction and deployed 7 equipment units , successfully completing the
resurfacing of 17 roads , totally up to 700000 m2 within less than one month.